Let's say you have a high-level finished goods assembly called FG1, which includes a component called Comp1 and a higher-level phantom assembly called Phantom1. Phantom1 itself includes a lower-level phantom assembly called Phantom2, which contains components Comp3 and Comp4. Here’s how you would set it up:
Create Material Master for FG1, Comp1, Phantom1, Phantom2, Comp3, and Comp4.
Set Special Procurement Key to 50 for Phantom1 and Phantom2.
Create BOM for FG1:
Include Comp1 and Phantom1 as components.
Set Phantom1 as a phantom assembly in its BOM.
Create BOM for Phantom1:
Include Comp2 and Phantom2 as components.
Set Phantom2 as a phantom assembly in its BOM.
Create BOM for Phantom2:
Include Comp3 and Comp4 as components.
Set both as normal components (no special settings needed).
By following these steps, you can effectively set up and manage phantom parts in SAP, streamlining your production planning and costing processes.